BOQ format in Excel: a bill of quantities template with columns, units, and a worked sample

Plenty of BOQs in India still start life in Excel, and when one goes wrong it's usually the way the sheet was built, not the arithmetic. This is a practical bill of quantities format for interior fit-out and civil work: the seven columns, how to split the sheet into sections, which unit each kind of work is measured in under IS 1200, how to build a rate, a worked sample whose numbers tie out, and the Excel habits that stop a total from quietly going wrong.

Boqos — Win more work. Stop the margin leaking.

A BOQ format in Excel that holds up A bill of quantities laid out as an Excel sheet. The formula bar shows cell F7 containing the formula ROUND of D7 times E7 to zero decimals, meaning amount equals quantity times rate rounded to whole rupees. Below it, column letters A to G sit over seven columns: item, description, unit, quantity, rate in rupees, amount in rupees, and remarks. Section B, flooring, has two lines: B.01 vitrified tiles 600 by 600 millimetres, 110 square metres at 1,180 rupees, amount 1,29,800, remark make as per sample; and B.02 tile skirting 100 millimetres high, 62 running metres at 240 rupees, amount 14,880, remark running metres not square metres. Its sub-total of 1,44,680 uses the formula SUBTOTAL 9 of F7 to F8. Section C, ceiling and painting, has C.01 gypsum board false ceiling, 96 square metres at 1,050 rupees, amount 1,00,800, and C.02 acrylic emulsion two coats, 240 square metres at 95 rupees, amount 22,800, with a sub-total of 1,23,600. Notes point out that units come from a drop-down list and that the amount column is a formula, never a typed number. A closing strip says quantities come from the measurement sheet and rates from the rate analysis, amount is always quantity times rate with sections rolled up by SUBTOTAL, and typing a number into the amount column makes the totals stop telling the truth. A BOQ format in Excel that holds up Seven columns, lettered sections, and amounts that are always formulas F7 fx =ROUND(D7*E7,0) Amount = Qty × Rate, rounded to ₹1 A B C D E F G 5 6 7 8 9 10 11 12 13 Item Description Unit Qty Rate ₹ Amount ₹ Remarks B FLOORING B.01 Vitrified tiles 600 × 600 mm sqm 110 1,180 1,29,800 Make as per sample B.02 Tile skirting, 100 mm high rmt 62 240 14,880 rmt, not sqm Sub-total B 1,44,680 =SUBTOTAL(9,F7:F8) C CEILING & PAINTING C.01 Gypsum board false ceiling sqm 96 1,050 1,00,800 Cut-outs included C.02 Acrylic emulsion, 2 coats sqm 240 95 22,800 Over 1 coat primer Sub-total C 1,23,600 =SUBTOTAL(9,F11:F12) ▲ units from a drop-down ▲ a formula, never typed Qty from the measurement sheet. Rate from the rate analysis. Amount is always Qty × Rate, and each section rolls up with SUBTOTAL. Type one number into the Amount column and the totals stop telling the truth.

Plenty of bills of quantities in India still begin as an Excel sheet, and a sheet built in a hurry breaks in familiar ways: amounts typed in by hand, units that change halfway down a column, a grand total that adds the sub-totals twice. The maths is easy. The hard part is building the sheet so it stays right as the job changes.

This is a practical BOQ format in Excel for interior fit-out and civil work: the columns, the sections, the units, how to price a line, a worked sample, and the mistakes that break a total. For the background (what a BOQ is, and why it’s the document the client signs), start with what a BOQ is in interior fit-out.

The seven columns of a BOQ in Excel

Every BOQ, whether it’s for an office fit-out or a boundary wall, comes down to the same seven columns. Keep them in this order so anyone you send the sheet to reads it the same way.

ColumnWhat goes in itHow it’s filled
A · Item no.A fixed reference: section letter plus line number (B.02)Typed
B · DescriptionThe work, specific enough to price and to check on siteTyped
C · Unitsqm, rmt, cum, kg, nosDrop-down list
D · QtyThe quantity taken off the drawingsLinked from the measurement sheet
E · Rate (₹)Cost per unit, including your marginLinked from the rate analysis
F · Amount (₹)Qty × RateFormula only
G · RemarksMake, drawing reference, exclusions, provisional or PCTyped

Description has to be specific: “Vitrified tiles 600 × 600 mm laid on cement mortar bed,” not “flooring.” A vague line can’t be priced or checked on site. Remarks is easy to skip, but it’s where arguments about scope get settled: the approved make, what’s excluded, which drawing the quantity came from.

Lay the workbook out as four linked sheets

A BOQ that holds up is four sheets that feed each other, not one long sheet:

  1. Measurement sheet: each line’s length, breadth and height, and the quantity they produce.
  2. Rate analysis: how each rate is built up.
  3. BOQ: the seven-column table in lettered sections, with a sub-total under each.
  4. Summary (abstract): one line per section, adding up to the works total, with tax below.
How the four sheets of a BOQ workbook link together A flow of four sheets. The measurement sheet, holding length, breadth and height for each line, feeds the quantity into the BOQ sheet. The rate analysis, holding material, labour, overheads and profit, feeds the rate into the BOQ sheet. The BOQ sheet holds sections A to D, with amount equal to quantity times rate, and feeds section totals into the summary sheet, which gives the works total. A strip at the bottom says each number lives in one place, so cells should be linked and never retyped. One workbook, four linked sheets Quantities and rates are worked out once, then linked into the BOQ — never retyped Measurement L × B × H per line Rate analysis material + labour + OH&P BOQ sheet sections A, B, C, D Amount = Qty × Rate Summary section totals → works total Qty Rate totals Each number lives in one place. Link the cells; never retype them.
Quantities are worked out on the measurement sheet and rates on the rate analysis; the BOQ only links to them, and the summary only adds up the BOQ's section totals.

Make the sections match how you’ll buy the work. For an interior fit-out that’s usually civil, flooring, false ceiling and painting, partitions, joinery and furniture, electrical, HVAC and plumbing; for civil work, earthwork, concrete, masonry, plaster and finishes. A BOQ split along likely sub-contract packages is easier to price, because each package can go out to sub-contractors for prices (Designing Buildings Wiki).

Measure each line in the right unit

In India the reference for units is IS 1200, the Bureau of Indian Standards’ method of measurement of building and civil engineering works. It comes in parts, one for each kind of work, and each part sets the unit and what to deduct. The ones that come up in a typical fit-out or civil BOQ:

WorkUnitWhere IS 1200 sets it
Earthwork (excavation, filling)cumPart 1
ConcretecumPart 2
Structural steel and ironworkkgPart 8
False ceilings and liningssqmPart 10
Flooring and dadosqmPart 11
Skirting (state the height)rmtPart 11
Painting walls and ceilings (distemper, emulsion)sqmPart 13
Painting and polishing woodwork and metalworksqmPart 15
Door and window shutterssqmPart 21
Workstations, fixtures, door sets priced as one itemnosNot an IS 1200 unit; a common fit-out practice. Say what one number includes

A few of IS 1200’s rules are worth copying into your measurement sheet even on private jobs:

  • Book dimensions in a consistent order: generally length, then breadth or width, then height, depth or thickness (Part 1).
  • Measure each dimension to the nearest 0.01 m, and work out areas to the nearest 0.01 sqm and volumes to the nearest 0.01 cum (Part 1).
  • Measure floors before skirting, dado or wall plaster goes on (Part 11, as amended).
  • Don’t deduct small voids. Part 11 makes no deduction from floor finishes for voids of 0.2 sqm or less.

The parts linked above are older editions (1973 to 1994) made public by Public.Resource.Org, and BIS may have revised some of them since. If your contract names a method of measurement, follow the contract, and check which edition and parts it refers to. Where nothing is stated, a note saying “measured as per IS 1200” saves an argument at billing time. If your clients think in sq ft and rft, that’s fine, but use one system for the whole BOQ.

For UK readers looking for a bill of quantities template: the rulebook there is the RICS New Rules of Measurement, where NRM2 covers detailed measurement for building works. NRM formally replaced SMM7 on 1 July 2013, though take-up of NRM2 has been limited and many practitioners still use SMM7 or their own methods (Designing Buildings Wiki). The seven-column layout works the same either way.

A worked sample BOQ

Here’s a small office fit-out laid out the way it would sit in the BOQ sheet. The rates are illustrative, not market rates; the structure and the arithmetic are the point.

ItemDescriptionUnitQtyRate (₹)Amount (₹)Remarks
ACivil
A.01Dismantle existing floor tiles, incl. debris removalsqm110859,350Debris carted off site
A.02115 mm brick wall in cement mortar 1:4sqm181,25022,500Up to 3.0 m high
A.0312 mm cement plaster 1:6 to new wallssqm3632011,520Both faces of A.02
Sub-total A43,370
BFlooring
B.01Vitrified tiles 600 × 600 mm on mortar bedsqm1101,1801,29,800Make as per approved sample
B.02Tile skirting, 100 mm highrmt6224014,880
Sub-total B1,44,680
CCeiling and painting
C.01Gypsum board false ceiling on GI framesqm961,0501,00,800Light cut-outs included
C.02Acrylic emulsion, 2 coats over 1 coat primersqm2409522,800Walls only
Sub-total C1,23,600
DJoinery and furniture
D.01Laminated flush door with hardwarenos414,50058,000Hardware from approved list
D.02Modular workstation 1,200 × 600 mmnos1218,5002,22,000Chairs excluded
Sub-total D2,80,000
Works total (A + B + C + D)5,91,650

Look at A.03: its quantity is both faces of the new wall in A.02 (18 sqm × 2 = 36 sqm), and the remark says so. The summary sheet carries one line per section to the works total of ₹5,91,650, and GST goes below that at the rate that applies to your contract. Confirm the rate with your CA rather than copying it from an old BOQ.

The formulas are short. The first two follow the figure at the top of this page, where B.01 sits in row 7 and B.02 in row 8. The works-total range is only an example, so point it at your own sheet’s Amount column, from the first line to the last:

CellFormulaWhat it does
F7=ROUND(D7*E7,0)Amount for one line, in whole rupees
F9=SUBTOTAL(9,F7:F8)Sub-total for section B
F30=SUBTOTAL(9,F6:F29)Works total, for a BOQ whose lines run from row 6 to row 29

ROUND rounds each amount to whole rupees (Microsoft), so the amounts you see are the amounts being added. SUBTOTAL(9, …) adds a range but ignores any other SUBTOTAL results inside it, so nothing is counted twice (Microsoft). That’s why the works total can run down the whole Amount column, sub-total rows and all, and still come out right. One catch: SUBTOTAL also leaves out rows hidden by a filter, so clear any filters before you read off a total.

How to price each line

The rate is where your margin is. Build each one on the rate-analysis sheet from four parts: material at current supplier rates plus a wastage allowance, labour per unit, sundries (adhesives, fixings, consumables, cartage), and overheads and profit as a percentage on top.

An illustrative build-up for B.01, per sqm: tiles with wastage ₹620, mortar bed and joint filler ₹150, labour ₹200, sundries and cartage ₹56, making ₹1,026; add 15% overheads and profit (₹154) and the rate is ₹1,180. When the tile price changes, you change one cell and the BOQ follows.

Take base numbers from your own past jobs first, then current supplier quotes. For government-style civil work, CPWD’s Delhi Schedule of Rates, on its publications page, is a useful cross-check. Treat any published schedule as a reference point, not your price: your costs depend on your city, suppliers and crew.

Some lines can’t be priced yet, because the client hasn’t chosen the tile or the design isn’t finished. Don’t guess a firm rate; mark them in Remarks. A provisional sum is an allowance for work not yet defined in enough detail to price (Designing Buildings Wiki). A prime cost (PC) sum is an allowance for work or materials from a supplier the client chooses, and the contract sum goes up or down by the difference once the actual cost is known (Designing Buildings Wiki).

Set the sheet up so the totals can’t drift

  • Units from a drop-down. Select the Unit column, go to Data > Data Validation, set Allow to List, and enter your units as the source (Microsoft). Nobody can type “Sqm.” in one row and “sq.m” in the next.
  • Freeze the header row with View > Freeze Panes, so the column names stay on screen (Microsoft).
  • Lock the formulas. By default, protecting a sheet locks every cell. So first unlock only the cells people should type in (Format Cells > Protection, clear Locked): Remarks on the BOQ, and the inputs on the measurement and rate-analysis sheets. Then use Review > Protect Sheet on each sheet. The formulas and links stay locked (Microsoft).
  • Date and number every issue. Put the revision and date in the header (“Rev 2, 21 Oct 2026”) and keep the old file, so you can show a client why the number moved.

Common mistakes that break a BOQ

  1. Lump-sum lines. “Electrical work: lump sum” hides every quantity in it. Use a lump sum only where a line really can’t be measured.
  2. Vague descriptions. “Painting” could mean one coat of distemper or three coats of emulsion. Say which.
  3. Mixed units. Skirting in rft on one sheet and rmt on another. One system, the whole way through.
  4. Typed-in amounts. One hard-typed number and that row no longer equals qty × rate. If a client negotiates a line down, change the rate, not the amount.
  5. SUM over sub-totals. SUM down a column that already holds section sub-totals counts the work twice. Use SUBTOTAL.
  6. Quantities with no working. Without a measurement sheet nobody can check a quantity, and on a running project someone will, because every RA bill is measured against these same BOQ lines.
  7. No exclusions. If chairs, approvals or rewiring aren’t included, say so in Remarks.

When Excel stops being enough

Excel works for one BOQ at a time. It gets harder once several jobs run at once: the same rates get retyped into every new file, variations get agreed on WhatsApp, and the BOQ the client signed stops matching what you bill. Our guide to the best BOQ software in India compares the options for that stage.

Boqos is quote-to-cash software for interior fit-out and design-build firms. You describe the scope or upload drawings, and Boqos builds the BOQ from India’s construction rate library, GST-aware and editable before you send it. From there it carries the job through proposal and client e-approval, priced and approved variations, and milestone invoicing, in one system instead of separate Excel files. There’s a 14-day free trial. But you don’t need software to start: a clean seven-column sheet with linked quantities and rates will carry a firm a long way.

The short version

Seven columns, lettered sections with sub-totals, and a summary sheet on top. Measure each line in its IS 1200 unit, build every rate from the bottom up, and keep quantities and rates on their own sheets, linked rather than retyped. Make Amount a formula, total with SUBTOTAL, and protect the sheet. Then the number the client signs is one you can defend line by line.